Documents

Inframark C&D Report

View original document →

Ebensburg Municipal Authority: February 2026 Monthly Report

Submitted by: Inframark Water Infrastructure Operations
Date of Report Submission: March 23rd, 2026
Prepared for: Ebensburg Borough Authority Members


Executive Summary

Inframark conducted regular leak detection throughout February using listening equipment in areas of concern. Several leaks were identified and repairs are being scheduled by the Public Works Director.

  • Margaret Street Leak (Feb 26): Repaired with Borough crews; no customers affected. Pipe was clamped without loss of pressure.
  • Emerald Estates Investigation: Leak suspected near storm drain culvert — none visible yet. Audit of water usage planned but insert meter (purchased 2019) is missing. Quote submitted for replacement meter.
  • Drinking Water Pumping Stations: Inspected regularly. Pumps/motors greased, packing glands checked, Ogden tank inspected for leaks/operations. Weekly sampling, flow recording, calibrations completed. All stations swept, cleaned, plowed, and salted during winter weather.
  • Sewer Lift Stations: Regular inspections performed. Faulty control panel heater found at Marine Center pumpstation — new heater ordered, pending installation. Pump runtime documented, generators inspected. Wet wells pumped down, flanges/seats checked — no leaks found. Floats/transducers at all three lift stations working properly. Basket screeners cleaned. Buildings swept and cleaned. All stations plowed/salted during winter events.

On the Radar (Upcoming Tasks):

  • Repair Beech Street leak
  • Repair Marian Street leak
  • Continue Leak Detection efforts

Operations & Compliance

Inframark met all state-mandated compliance requirements:

  • Assisted Borough crews with leak repairs.
  • Submitted monthly compliance reports to PA DEP.
  • Collected and analyzed 9 bacteriological samples (zero total coliform positives).
  • Monitored chlorine levels: minimum 1 sample/week required (≥0. 20mg/L free chlorine). Four samples collected in February — all met or exceeded minimum.
  • Calibrated handheld instrumentation per PA DEP rules.
  • Collected comparative grab samples to verify accuracy of continuous chlorine analyzers.
  • Monitored overall water quality in distribution system.

Zone Meter Water Usage (Gallons Per Minute)

Date Total High System Avg Flow High System Zone Meter Avg Flow Low System Meter Avg Flow
January 2026 560 GPM 177 GPM 200 GPM
February 2026 618 GPM 281 GPM 202 GPM

Note: February showed increased flow across all zones compared to January.


Maintenance & Repair Activities

  • Cleaned out water valve boxes
  • Flushed fire hydrant at LB Water
  • Uncovered manhole in Hillcrest
  • Dug up Emerald Estates valves
  • Greased pumps and motors
  • Cleaned lift station baskets
  • Conducted generator inspections
  • Performed snow removal

Financial Update

Maintenance Expenditures (February 2026)

Vendor Expense Description
Amazon $1,018. 20 Generator/hydrant bore camera/valve tools
Wal-Mart $226. 05 Batteries/generator cord/work light
Sunoco $6. 17 Fuel for generator

Caps For WTP (Water Treatment Plant) Budget Tracking

Item Contract Total per Year Previous Balance Total Spent This Month Remaining Balance
Maintenance Cap $5,000. 00 $4,466. 87 $1,250. 42 $3,216. 45

Note: The “Previous Balance” appears to be cumulative spending prior to this month. After adding February’s $1,250. 42 spend, remaining balance is $3,216. 45 — suggesting possible rounding or adjustment not detailed.


This report reflects proactive maintenance, regulatory compliance, and transparent financial tracking for Ebensburg’s water infrastructure operations during February 2026. Residents can expect continued focus on leak resolution and system reliability.

← Back to Documents