Documents

Inframark Report

View original document →

Ebensburg PA Municipal Authority: June 2022 Management, Operations & Maintenance Report

Report Date: July 25, 2022 Prepared by: Inframark Water Infrastructure Operations

Executive Summary & Key Events

  • Water Treatment Volume: The Ebensburg water treatment plant treated 23,593,000 gallons of reservoir water in June. This averages to 786,433 gallons per day, a decrease from previous months due to recent leak repairs in the distribution system.
  • Power Outages: Two power outages occurred, causing a fault in the DAF recycle pump motor VFD. The issue was resolved by resetting the VFD, though it caused mild settled turbidity issues. A concern was noted regarding the lower reservoir VFD's inability to start/stop automatically.
  • Swimming Pool Issue: On June 13, the director of recreation reported chlorine level issues at the public pool. Inframark identified a failed chlorine feed pump and missing components. They installed a spare pump from the WTP, restoring normal conditions within 24 hours. A new pump was ordered and installed on June 27.
  • DEP Site Visit: On June 16, representatives from the Department of Environmental Protection (DEP) Bureau of Safe Drinking Water visited to collect a sample for cyanotoxin analysis in the raw source water.
  • Hold Study: Inframark conducted a hold study to determine if the produced water could meet all quality parameters after 10 days. Results indicated that the water meets all standards even after 10 days of age.
  • Presentation: On June 23, Inframark’s senior technical manager presented options to the borough manager and Stiffler McGraw to address recurring disinfection by-product issues.

Operations & Compliance

  • Daily Flow: The plant is currently treating between 750,000 and 850,000 gallons of water per day.
  • Reporting: 2021 Chapter 110 reports and the Consumer Confidence Report have been submitted to PA DEP.
  • Monitoring: Backwash flow rates, filter media, and online instrument flow are monitored daily. Flows and chemical feed rates are adjusted daily to meet system demands.
  • Compliance Reporting: Monthly compliance reports (Monthly Operating Report) are compiled from over 20,000 data points and sent to the state. The July report will be submitted by August 10, 2022.
  • Sampling:
    • Samples for Inorganic, Volatile Organic, and Synthetic Organic Compounds were collected; all results were non-detects or well below Maximum Contaminant Levels.
    • Nine bacteriological samples were collected in June, with zero total coliform positives.
    • Four chlorine samples were collected in the distribution system, all meeting the minimum requirement of 0. 20mg/L free chlorine.
  • Instrument Calibration: Online and lab instrumentation were calibrated to meet PA DEP requirements. Comparative grab samples were collected for chlorine analyzers, turbidimeters, and pH analyzers.
  • Filter Evaluation: The second quarter filter evaluation for Filter #1 was completed, finding it in excellent condition and meeting all design specs.

Maintenance & Repair

  • Work Orders: Inframark staff completed 75 work orders in June.
  • Preventive Maintenance:
    • Daily equipment checks and plant rounds were performed.
    • Plant safety inspection was completed for the month.
    • Centrifuge was run weekly.
    • Grass and weeds were cut around the plant.
    • Control building floors were swept and mopped weekly.
    • Mixers in basin #4 were pulled due to debris caught in blades.
  • Specific Tasks Completed:
    • Lubricated blower motor, DAF recycle pump, and DAF scrapper.
    • Performed ladder inspections and annual fire extinguisher inspection.
    • Installed new battery backups for SCADA.
    • Exercised sump pumps.
    • Conducted eye wash/safety shower inspections.
    • Greased clarifier drives and finished water pumps/motors.
    • Tested chlorine room alarm.
    • Removed lagoon vault sludge.
    • Alternated finished water pumps weekly.
    • Cleaned pH and turbidity meters weekly.
    • Performed jar testing to optimize chemical usage.
    • Cleaned lab glassware.
    • Monitored filter beds for deficiencies.
  • Borough Crews: Summer maintenance crews completed about 50% of the grass-knocking-down task around the facility.

Financial Update

  • Maintenance Expenditures (Wastewater):
    • Total spent in June: $1,974. 38
    • Major expenses included Lubrication Engineers ($915. 33), Ace Hardware ($272. 36), and State Chemical ($535. 04).
  • Maintenance Expenditures (Water Treatment Plant):
    • Total spent in June: $1,251. 05
    • Major expenses included Home Depot ($510. 23), Amazon ($218. 26), and LB Water ($198. 76).
  • Caps (WTP):
    • Contract Total per Year: $26,010. 00
    • Previous Balance: $20,952. 60
    • Remaining Balance: $19,701. 55

Health & Safety

  • Wastewater Facility: Employees have worked 6,358 days without a lost time injury or recordable incident. Daily tailgate meetings were held.
  • Water Treatment Plant: No accidents occurred in June. Personnel have worked 881 days (2 years, 5 months) without an accident/injury.
  • Training: Weekly tailgate meetings, COVID-19 updates, Personal Protective Equipment training, and Lead and Copper SOP reviews were conducted.

Personnel

  • Wastewater Facility:
    • Jerry Shupe Jr. : Vice President, Mid-Atlantic Region
    • Mike Montgomery: Plant Manager (PA Class A, E Subclass 1,2,3,4)
    • Sharon Burkett: Lab Manager (PA Class A, E Subclass 1,2,3,4,5)
    • Randy Lauer: Operator (PA Class A, E Subclass 1,2,3,4)
    • Ryan Lanzendorfer: Operator in Training (None)
    • Kyle Smiley: Operator in Training (None)
  • Water Treatment Plant:
    • Luke Byrne: Water Plant Manager (PA Class A, E, Water Subclass 1,7,8,10,11)
    • Kyle Smiley: Operator (PA Class A, E, Subclass 1)
    • Ryan Lanzendorfer: Operator in Training

Appendix

  • June’s 2022 Discharge Monitoring Report is available upon request.
← Back to Documents