Documents

Inframark Reports

View original document →

Ebensburg Wastewater Treatment Plant (WWTP) Report - June 2023

Submitted by: Inframark Water Infrastructure Operations Date of Report: July 24, 2023

Executive Summary

  • Volume Treated: The plant treated a total of 13,421,000 million gallons of wastewater in June.
  • Daily Average: This equates to an average of 447,000 million gallons per day.
  • Compliance: All testing and operational requirements were met for the month.
  • Sludge Disposal: 9. 217 tons of sludge were sent to the landfill.
  • Maintenance: Staff replaced a failing aeration valve on SBR tank #1.

Operations & Maintenance

  • Testing Schedule:
    • SBR tank testing for process control occurs on Mondays, Wednesdays, and Fridays.
    • Influent and effluent compliance testing for DEP reporting occurs on Tuesdays and Thursdays.
  • Reporting: All data is entered into WIMS daily for E-DMR monthly reporting. Monthly reports are sent electronically to the DEP by the 28th of each month.
  • Routine Checks: Plant rounds and equipment checks were performed twice daily per shift.
  • Equipment Status:
    • Blowers, screening units, U. V. units, and influent/effluent samplers were operating properly.
    • The centrifuge was run weekly.
  • Cleaning:
    • Influent screening unit was hosed and cleaned daily.
    • Floors in the influent building, centrifuge building, and sludge dumpster area were swept and hosed.
    • U. V. trough, bulbs, and sensors were cleaned twice during the month.
  • Work Orders: A total of 281 work orders were completed for the month.

Financial Update

  • Total Maintenance Expenditures: $1,916. 67
  • Key Expenses:
    • Applied Technologies: $1,106. 38 (Spare motor for screening unit)
    • Grainger: $276. 47 (Cable and fittings for mixers)
    • Wal-Mart: $162. 06 (Office and cleaning supplies)
    • NAPA: $165. 21 (New battery for loader)

Health & Safety

  • Accident Record: There were no accidents in June. Personnel have worked 6,740 days (18 years and 3 months) without an accident or injury.
  • Training & Inspections:
    • Weekly tailgate meetings were held.
    • Topics covered included COVID-19 updates, Personal Protective Equipment (PPE), and heat stroke awareness.
    • Monthly safety inspections, fire extinguisher checks, and inspections of diesel, generator, propane tanks, and ladders were completed.

On the Radar (Upcoming Tasks)

  • Replacing wiper seals on the U. V. wiper system.
  • Installing 3 new SBR aeration valves to replace existing ones.
  • Removing mixers and sludge pumps from tanks to change oil.

Ebensburg Water Treatment Plant (WTP) Report - June 2023

Submitted by: Inframark Water Infrastructure Operations Date of Report: July 24, 2023

Executive Summary

  • Volume Treated: The plant treated 27,379,000 gallons of reservoir water.
  • Daily Average: This equates to an average of 912,633 gallons per day.
  • Production Increase: June 2023 production shows an increase of 126,200 gallons per day compared to June 2022.
  • Purchased Water: An average of 63,608 gallons per day was purchased from Saltlick and blended into the distribution system.
  • Compliance Assistance: Staff assisted the public works director with the Initial Demonstration of Capability for analyzing Chlorine (Method 334. 0).

Key Events & Maintenance

  • Mainline Break (June 2nd): High water flow alarms were triggered. Inframark located the break, assisted in isolating the leak, and recommended a boil water notice due to the need to cut the mainline and loss of positive pressure.
  • Drought Watch: PA DEP issued a "Drought Watch" for all 67 counties in Pennsylvania. The upper reservoir is currently roughly -2. 2ft below the spillway. Inframark is reviewing the EMA’s Drought Contingency Plan with Borough staff.
  • Cyanotoxin Monitoring (June 20th): PA DEP collected raw water samples; there were no detects.
  • Gate Repair: Inframark thanked Josh for repairing an unsecured/damaged upper reservoir gate noted by PA DEP. Signage is being worked on for the gate and WTP facility.
  • Equipment Service: A full service was performed on the WTP air scour blower unit, including oil/grease changes and belt tensioning.
  • Flow Adjustment (June 21st): The upper reservoir stream flow valve was shut to meet the 270,000 gallon per day downstream flow requirement.
  • Filter Evaluation (June 23rd): The second quarter filter bed evaluation on filter #3 was completed. The filter is in excellent condition.
  • Pool Issue: Staff fixed a chlorine feed issue at the borough pool.

Operations & Compliance

  • Production Range: Plant production fluctuated between 817,000 and 1,188,000 gallons/day.
  • Filter Washing: Filters are washed every 144 hours (once per week).
  • Monitoring: Clarifiers, flows, chemical feed rates, and online instrument flows are monitored daily.
  • Bacteriological Sampling: Nine samples were collected and analyzed; zero were found to be total coliform positive.
  • Chlorine Monitoring: Four samples were collected in June, all meeting the minimum requirement of 0. 20mg/L free chlorine.
  • Water Loss Study: Inframark submitted a study/plan to PA DEP regarding historical water loss and is awaiting a response.
  • Instrument Calibration: Online and lab instrumentation were calibrated to conform to PA DEP requirements.

Financial Update

  • Total Maintenance Expenditures: $3,032. 06 (Spent this month)
  • Contract Total per Year: $26,522. 00
  • Remaining Balance: $20,031. 11
  • Key Expenses:
    • Hach Company: $1,128. 58 (pH sensor)
    • Ram Industrial Services: $855. 52 (Motor for clarifier drive)
    • The Meter Guy: $650. 00 (Flow meter calibrations)
    • Harbor Freight: $142. 36 (Hoist lift straps/pressure gauges/magnet)

Health & Safety

  • Accident Record: There were no accidents in June. Personnel have worked 1,246 days (3 years and 6 months) without an accident or injury.
  • Training & Inspections:
    • Weekly tailgate meetings were held.
    • Topics covered included COVID-19 updates, PPE, and a Drought Contingency Plan (DCP) review.
    • Inspections included eye wash/safety showers, fire extinguishers, SCBA equipment, and ladders.

Personnel

  • Luke Byrne: Water Plant Manager (PA Class A, E, Water Subclass 1,7,8,10,11)
  • Kyle Smiley: Operator (PA Class A, E, Subclass 1)
  • Jacob Dumm: Operator in training (Preparing for Exam)

On the Radar (Upcoming Tasks)

  • Service clarifiers.
  • Address PA DEP inspection correctives.
  • Update Drought Contingency Plan.
  • Bulk chemical tank cleanout.
  • DAF scrapper adjustments/repairs.
← Back to Documents