Documents

Inframark Reports

View original document →

Ebensburg Wastewater Treatment Plant (WWTP) Report - July 2023

Submitted by: Inframark Water Infrastructure Operations Date of Report: July 28, 2023

Executive Summary

  • Volume Treated: The plant treated a total of 16,044,800 gallons of wastewater in July.
  • Daily Average: This equates to an average of 510,000 gallons per day.
  • Compliance: All testing and operational requirements were met for the month.
  • Sludge Disposal: 8. 949 tons of sludge were sent to the landfill via centrifuge operation.

Operations & Maintenance

  • Testing Schedule:
    • SBR tank testing for process control occurs on Mondays, Wednesdays, and Fridays.
    • Influent/effluent compliant testing for DEP reporting occurs on Tuesdays and Thursdays.
    • All data is entered into WIMS daily for E-DMR monthly reporting.
  • Plant Rounds: Daily equipment checks were performed twice per shift.
  • Equipment Status: Screening units, U. V. units, and influent/effluent samplers were operating properly with no blockages.
  • Maintenance Tasks:
    • Blowers were checked for oil and belts daily.
    • The centrifuge was run weekly.
    • Influent screening units were hosed and cleaned daily.
    • Floors in the influent building, centrifuge building, and sludge dumpster area were swept and hosed.
    • U. V. troughs, bulbs, and sensors were cleaned twice during the month.
    • Repairs: Three SBR mixers were sent out for repair.

Financial Update

  • Work Orders: 341 work orders were completed for the month.

Maintenance Expenditures:

  • Kaza: $1,054. 70 (Confined space meter/gas meter)
  • Dodson Electric: $765. 80 (Electrical work and new contactors for SBR mixers)
  • Lubrication Engineers: $767. 33 (2-5-gallon buckets of oil for plant blowers)
  • Home Depot: $210. 94 (4" cordless grinder)
  • NAPA: $130. 94 (5 gallon of gear oil for gearboxes)
  • Scanlan: $50. 10 (Fuses for mixers, screening unit)
  • Hoovers Garage: $39. 50 (2- Lawn mower blades)
  • Get - Go: $36. 45 (Gas for mower, weed eater)
  • Tractor Supply: $24. 34 (Snap rings for SBR mixers)
  • Ace Hardware: $9. 33 (2" PVC pipe)
  • LB Water: $2. 12 (Nuts for aeration valve)

Caps For WWTP Budget:

  • Contract Total per Year: $25,691. 76
  • July 2023 Spend: $3,091. 55
  • Contract Year to Date: $16,408. 94
  • Remaining Balance: $9,282. 82

Health & Safety

  • Accidents: There were no accidents in July.
  • Safety Record: Personnel have worked 6,770 days (18 years 4 months) without an accident or injury.
  • Training: Weekly tailgate meetings were held.

Personnel

  • Michael Montgomery: Plant Manager (PA Class A, E, Wastewater Subclass 1,2,3,4)
  • Sharon Burkett: Lab Supervisor (PA Class A, E, Wastewater Subclass 1,2,3,4,5)
  • Kyle Smiley: Operator (PA Class A, E, Water Subclass 1)
  • Jake Dumm: Operator in Training

Ebensburg Water Treatment Plant (WTP) Report - July 2023

Submitted by: Inframark Water Infrastructure Operations Date of Report: August 28, 2023

Executive Summary

  • Volume Treated: The plant treated 26,670,000 gallons of reservoir water.
  • Daily Average: This equates to an average of 860,323 gallons per day.
  • Production Increase: July 2023 production shows an increase of 100,000 gallons per day compared to July 2022.
  • Purchased Water: An average of 57,247 gallons per day was purchased from Saltlick and blended into the distribution system.

Key Events & Operations

  • July 5th: Disinfection by-product samples were collected. Results were under half the maximum contaminant level for HAA5’s, allowing compliance without a public notice.
  • July 7th: Inframark began operating the Ogden tank chlorine booster station.
  • July 12th: A tour was hosted for Saint Francis University’s water reclamation academy, led by Professor Mr. Tasker and his students.
  • July 13th: The Emerald estates pumping station was found in alarm and failing to pump. Borough staff helped fix the motor issues and restore the dialer for call-outs.
  • July 26th: PA DEP collected raw water samples for cyanotoxins; there were no detects.
  • Inspections:
    • Hartford Steam Boiler Inspection and Insurance Company conducted annual boiler inspections; both passed.
    • Kaza Fire Equipment performed annual inspections and renewed four fire extinguishers at the WTP.
  • Flow Requirements: The downstream by-pass flow valve was operated to meet the instream flow requirement of 270,000 GPD.

Operations & Maintenance

  • Production Range: Plant production fluctuated between 776,000 and 920,000 gallons/day.
  • Filter Maintenance: Filters are washed every 144 hours (once per week).
  • Monitoring: Clarifiers, chemical feed rates, and overnight flows were monitored daily.
  • Work Orders: Inframark staff completed 94 work orders in July.
    • Greased DAF recycle pump and scraper.
    • Inspected fire extinguishers, SCBA gear, ladders, and boiler jackets.
    • Repaired Ogden tank chlorine feed line and rebuilt LMI pump.
    • Cleaned clarifier troughs and pH/turbidity meters weekly.
    • Monitored filter bed expansion.

Financial Update

  • Maintenance Expenditures:
    • Instrulogic: $1,096 (DAF VFD reprogram)

Caps For WTP Budget:

  • Contract Total per Year: $26,522. 00
  • Previous Balance: $20,031. 11
  • Total Spent This Month: $1,096
  • Remaining Balance: $18,935. 11

Health & Safety

  • Accidents: There were no accidents in July. (Note: Report text mentions "no accidents in the month of June" but is dated August 28, 2023 for July report; context implies July safety record).
  • Safety Record: Personnel have worked 1,277 days (3 years 7 months) without an accident or injury.
  • Training: Weekly tailgate meetings, COVID-19 updates, and Emergency Action Plan reviews were conducted.

Personnel

  • Luke Byrne: Water Plant Manager (PA Class A, E, Water Subclass 1,7,8,10,11)
  • Kyle Smiley: Operator (PA Class A, E, Subclass 1)
  • Jacob Dumm: Operator in training (Preparing for Exam)
← Back to Documents