Inframark Reports
View original document →
Ebensburg Wastewater Treatment Plant (WWTP) Report - July 2023
Submitted by: Inframark Water Infrastructure Operations Date of Report: July 28, 2023
Executive Summary
- Volume Treated: The plant treated a total of 16,044,800 gallons of wastewater in July.
- Daily Average: This equates to an average of 510,000 gallons per day.
- Compliance: All testing and operational requirements were met for the month.
- Sludge Disposal: 8. 949 tons of sludge were sent to the landfill via centrifuge operation.
Operations & Maintenance
- Testing Schedule:
- SBR tank testing for process control occurs on Mondays, Wednesdays, and Fridays.
- Influent/effluent compliant testing for DEP reporting occurs on Tuesdays and Thursdays.
- All data is entered into WIMS daily for E-DMR monthly reporting.
- Plant Rounds: Daily equipment checks were performed twice per shift.
- Equipment Status: Screening units, U. V. units, and influent/effluent samplers were operating properly with no blockages.
- Maintenance Tasks:
- Blowers were checked for oil and belts daily.
- The centrifuge was run weekly.
- Influent screening units were hosed and cleaned daily.
- Floors in the influent building, centrifuge building, and sludge dumpster area were swept and hosed.
- U. V. troughs, bulbs, and sensors were cleaned twice during the month.
- Repairs: Three SBR mixers were sent out for repair.
Financial Update
- Work Orders: 341 work orders were completed for the month.
Maintenance Expenditures:
- Kaza: $1,054. 70 (Confined space meter/gas meter)
- Dodson Electric: $765. 80 (Electrical work and new contactors for SBR mixers)
- Lubrication Engineers: $767. 33 (2-5-gallon buckets of oil for plant blowers)
- Home Depot: $210. 94 (4" cordless grinder)
- NAPA: $130. 94 (5 gallon of gear oil for gearboxes)
- Scanlan: $50. 10 (Fuses for mixers, screening unit)
- Hoovers Garage: $39. 50 (2- Lawn mower blades)
- Get - Go: $36. 45 (Gas for mower, weed eater)
- Tractor Supply: $24. 34 (Snap rings for SBR mixers)
- Ace Hardware: $9. 33 (2" PVC pipe)
- LB Water: $2. 12 (Nuts for aeration valve)
Caps For WWTP Budget:
- Contract Total per Year: $25,691. 76
- July 2023 Spend: $3,091. 55
- Contract Year to Date: $16,408. 94
- Remaining Balance: $9,282. 82
Health & Safety
- Accidents: There were no accidents in July.
- Safety Record: Personnel have worked 6,770 days (18 years 4 months) without an accident or injury.
- Training: Weekly tailgate meetings were held.
Personnel
- Michael Montgomery: Plant Manager (PA Class A, E, Wastewater Subclass 1,2,3,4)
- Sharon Burkett: Lab Supervisor (PA Class A, E, Wastewater Subclass 1,2,3,4,5)
- Kyle Smiley: Operator (PA Class A, E, Water Subclass 1)
- Jake Dumm: Operator in Training
Ebensburg Water Treatment Plant (WTP) Report - July 2023
Submitted by: Inframark Water Infrastructure Operations Date of Report: August 28, 2023
Executive Summary
- Volume Treated: The plant treated 26,670,000 gallons of reservoir water.
- Daily Average: This equates to an average of 860,323 gallons per day.
- Production Increase: July 2023 production shows an increase of 100,000 gallons per day compared to July 2022.
- Purchased Water: An average of 57,247 gallons per day was purchased from Saltlick and blended into the distribution system.
Key Events & Operations
- July 5th: Disinfection by-product samples were collected. Results were under half the maximum contaminant level for HAA5’s, allowing compliance without a public notice.
- July 7th: Inframark began operating the Ogden tank chlorine booster station.
- July 12th: A tour was hosted for Saint Francis University’s water reclamation academy, led by Professor Mr. Tasker and his students.
- July 13th: The Emerald estates pumping station was found in alarm and failing to pump. Borough staff helped fix the motor issues and restore the dialer for call-outs.
- July 26th: PA DEP collected raw water samples for cyanotoxins; there were no detects.
- Inspections:
- Hartford Steam Boiler Inspection and Insurance Company conducted annual boiler inspections; both passed.
- Kaza Fire Equipment performed annual inspections and renewed four fire extinguishers at the WTP.
- Flow Requirements: The downstream by-pass flow valve was operated to meet the instream flow requirement of 270,000 GPD.
Operations & Maintenance
- Production Range: Plant production fluctuated between 776,000 and 920,000 gallons/day.
- Filter Maintenance: Filters are washed every 144 hours (once per week).
- Monitoring: Clarifiers, chemical feed rates, and overnight flows were monitored daily.
- Work Orders: Inframark staff completed 94 work orders in July.
- Greased DAF recycle pump and scraper.
- Inspected fire extinguishers, SCBA gear, ladders, and boiler jackets.
- Repaired Ogden tank chlorine feed line and rebuilt LMI pump.
- Cleaned clarifier troughs and pH/turbidity meters weekly.
- Monitored filter bed expansion.
Financial Update
- Maintenance Expenditures:
- Instrulogic: $1,096 (DAF VFD reprogram)
Caps For WTP Budget:
- Contract Total per Year: $26,522. 00
- Previous Balance: $20,031. 11
- Total Spent This Month: $1,096
- Remaining Balance: $18,935. 11
Health & Safety
- Accidents: There were no accidents in July. (Note: Report text mentions "no accidents in the month of June" but is dated August 28, 2023 for July report; context implies July safety record).
- Safety Record: Personnel have worked 1,277 days (3 years 7 months) without an accident or injury.
- Training: Weekly tailgate meetings, COVID-19 updates, and Emergency Action Plan reviews were conducted.
Personnel
- Luke Byrne: Water Plant Manager (PA Class A, E, Water Subclass 1,7,8,10,11)
- Kyle Smiley: Operator (PA Class A, E, Subclass 1)
- Jacob Dumm: Operator in training (Preparing for Exam)