Inframark WTP Report
View original document →
Ebensburg Municipal Authority: February 2025 WTP Monthly Report
Date: March 24, 2025 Submitted by: Luke Byrne, Inframark
Executive Summary & Operations
- Water Production: The plant treated 35,991,000 gallons in February (avg. 1,285,393 gallons/day). This is an increase of 133,083 gallons per day compared to the same time last year.
- Purchased Water: An average of 187,910 gallons per day were purchased from Saltlick to blend into the system due to excessive water loss.
- Maintenance Issues:
- A leak near the Water Treatment Plant (WTP) was discovered on February 6th. Borough crews tightened a leaking clamp, but a nearby valve is also leaking and may require a complete replacement.
- Staff repaired the raw water valve's 4-20mA feedback loop by installing a new potentiometer.
- The Caustic bulk chemical tank was cleaned out to resolve clogged feed lines.
- Awards: The plant was selected again for the prestigious Aera Wide Optimization Program (AWOP) Award. Operators Kyle Smiley and Anthony Perott will accept the award on March 24th.
- Water Quality: UCMR5 sampling for PFAS and Lithium was conducted on January 22 with no detectable results.
- Reservoir Levels: The upper reservoir level is at -6 ft, an increase of 2 ft from the previous month due to precipitation and snow melt.
- Compliance:
- Monthly Operating Report (MOR) submitted to PA DEP.
- Nine bacteriological samples were collected; zero were total coliform positive.
- Four chlorine samples were collected, all meeting the minimum requirement of 0. 20mg/L.
- A study on historical water loss was submitted to PA DEP on 12-20-22; awaiting response.
Maintenance & Repair
Inframark staff completed 72 work orders in February, including:
- Fire extinguisher and ladder inspections.
- Sump pump exercises.
- Caustic tank clean out.
- Raw water valve repairs.
- DAF lightning mixer oil level inspections.
- DAF air saturation adjustments and lagoon vault cleaning.
- Grease clarifier drives and cleaned troughs.
- Chlorine room alarm test.
- Greased finished water pumps/motors.
- Weekly cleaning of pH and turbidity meters.
- Jar testing for chemical optimization.
- Snow removal and salting walkways.
Financial Update
Maintenance Expenditures:
- Water service professionals: $2,618. 63 (DAF/cleaner)
- VAG USA LLC: $582. 67 (Raw water valve rebuild kit)
- Voltronics INC. : $553. 67 (1 K potentiometer)
- Tractor Supply: $171. 36 (Caustic tank clean out)
- Ace Hardware: $32. 46 (Raw water valve wiring)
Caps for WTP:
- Maintenance Cap: Contract total is $25,950. 84. With $3,958. 79 spent this month, the remaining balance is $21,633. 32.
- Chemical Cap: Contract total is $93,423. 12. With $5,904. 45 spent this month, the remaining balance is $76,743. 67.
Health & Safety
- There were no accidents in January. Personnel have worked 1,855 days (5 years, 2 months) without an accident or injury.
- Training included weekly tailgate meetings, slips/trips/falls prevention, and UCMR data review.
Personnel
- Kyle Smiley: Operator (PA Class A, E, Subclass 1,10,11,12)
- Tony Perott: Operator (PA Class C, E, Water Subclass 1,6,7,8,12)
- Matthew Hull: Operator in Training (Training for PA DEP exam)
- Shawn Jones: Operator in Training (Training for PA DEP exam)
- Luke Byrne: Project Manager (PA Class A, E, Water Subclass 1,7,8,10,11,12; PA Class A, E, Wastewater)