Inframark WTP Report
View original document →
Ebensburg Municipal Authority: February 2026 WTP Monthly Report
Date: March 23rd, 2026 Submitted by: Luke Byrne, Inframark
Executive Summary
During February 2026, the Ebensburg water treatment plant treated a total of 34,716,000 gallons of reservoir water. This equates to an average daily production of 1,239,857 gallons.
- Water Purchases: An average of 111,357 gallons per day were purchased from Saltlick and blended into the distribution system. This volume was higher than normal due to Nanty Glo purchasing water.
- Nanty Glo Supply: On February 24th, Nanty Glo began buying water at a rate of 150 GPM.
- Filter Evaluation: A quarterly evaluation of Filter #1 was conducted on February 9th. The troughs, filter media, and air scour system were found to be in excellent condition with no deficiencies or anomalies.
- Maintenance: Staff replaced a failing pH probe on the raw water line.
- Water Quality: Annual PFAS samples were collected with no detectable results.
- Reservoir Status: The upper reservoir water level is currently 7 feet below full pool level.
- Construction Delays: Weather conditions have delayed Greenland Construction from working on the upper reservoir intake valves. A downed tree also needs removal to gain access to the intake.
- Community Engagement: Inframark hosted a tour of the WTP facility for the Saint Francis University Environmental Engineering class.
Operations & Compliance
- Reporting: Monthly compliance reports (Monthly Operating Report) containing over 20,000 data points were submitted to the PA DEP.
- Monitoring: Turbidity levels were continuously monitored for each filter, with 2,688 readings collected in February; all were in compliance. Primary and secondary contaminant levels were monitored with no exceedances of maximum contaminant levels.
- Instrumentation: Online and lab instruments were calibrated to meet PA DEP requirements. Comparative grab samples were collected to ensure the accuracy of continuous chlorine analyzers, turbidimeters, and pH analyzers.
- Plant Production: Daily production fluctuated between 1,197,000 and 1,288,000 gallons.
- Routine Tasks: Daily process control analysis, backwash flow monitoring, clarifier sludge content checks, and chemical feed adjustments were performed.
Maintenance & Repair
Inframark staff completed 82 work orders in February, including:
- Fire extinguisher and ladder inspections.
- Sump pump exercises.
- Painting of the lab floor.
- Replacement of the raw water pH probe.
- Cleaning of the DAF unit, clarifier troughs, and facility.
- Eye wash/safety shower inspections.
- Greasing of clarifier drives and finished water pumps/motors.
- Chlorine room alarm test.
- Weekly cleaning of pH and turbidity meters.
- DAF sump level sensor verifications.
- Monitoring of filter bed expansion.
Financial Update
Maintenance Expenditures:
- Ace Hardware: $218. 25 for fittings/tubing for frozen water line repairs.
- Long Barn: $156. 45 for water line fittings.
Caps for WTP Budget Status:
- Maintenance Cap:
- Contract Total per Year: $26,664. 12
- Previous Balance: $25,896. 20
- Total Spent This Month: $374. 70
- Remaining Balance: $25,521. 50
- Chemical Cap:
- Contract Total per Year: $95,990. 76
- Previous Balance: $81,082. 71
- Total Spent This Month: $8,264. 45
- Remaining Balance: $72,818. 26
Health & Safety
- There were no accidents in February.
- Personnel have worked 2,220 days (6 years and 2 months) without an accident or injury.
- Ongoing safety activities include weekly tailgate meetings, safety flash reports, and weekly process control meetings.
Personnel
The following staff members are listed with their titles and certifications:
- Kyle Smiley (Operator III): PA Class A, E, Water Subclass 1,10,11,12; PA Class A, E, Wastewater Subclass 1.
- Tony Perott (Operator II): PA Class C, E, Water Subclass 1,6,7,8,12.
- Shawn Jones (Mechanic II): Training for PA DEP exam.
- Joseph Pompa (Operator in Training): Training for PA DEP exam.
- Cody Williams (Operator): PA Class E Water Subclass 12.
- Luke Byrne (Project Manager): PA Class A, E, Water Subclass 1,7,8,10,11,12; PA Class A, E, Wastewater.
On the Radar (Upcoming Items)
- DAF Spare parts
- Upper reservoir inlet valves
- SCADA upgrades
- Lighting