Documents

Inframark WTP Report

View original document →

Ebensburg Municipal Authority: July 2025 WTP Monthly Report

Date: August 25, 2025 Submitted by: Luke Byrne, Inframark

Executive Summary & Operations

  • Water Production: The plant treated 36,009,000 gallons of reservoir water in July (avg. 1,161,581 gallons/day).
  • Purchased Water: An average of 231,822 gallons per day were purchased from Saltlick and blended into the system. This volume is higher than normal because Nanty Glo is buying water from Ebensburg.
  • Nanty Glo Interconnect:
    • Nanty Glo shut off their emergency interconnect on July 2nd.
    • They reopened it on July 20th requesting 300 GPM due to a filter failure.
    • Staff have been operating the WTP at full permit capacity to meet demand. Nanty Glo has exceeded the 15-day purchase limit for an emergency interconnect.
  • Reservoir Level: The upper reservoir water level is at -2 ft.

Maintenance & Repairs

Inframark staff completed 56 work orders in July. Key activities included:

  • Equipment Issues:
    • A Flygt pump in the lagoon wet well suffered a seal failure. The 20-year-old pump was sent to Ram for evaluation; the rebuild cost over 50% of a new unit, so a new pump has been ordered.
    • On July 3rd, the raw water valve was not functioning properly due to a faulty 4-20 mA feedback instrument. A new device was installed and is working correctly.
    • #2 pump at Saltlick tripped on low voltage but has since operated properly.
  • Routine Maintenance:
    • Fire extinguisher and ladder inspections.
    • Sump pumps exercised.
    • DAF Air saturation adjustments and sump level sensor verifications.
    • Lagoon motor pull, vault cleaning, and float adjustments.
    • Greasing of clarifier drives, finished water pumps/motors, and all pump station motors.
    • Cleaning of clarifier troughs, pH/turbidity meters, and the facility.
    • Jar testing to optimize chemical usage.

Compliance & Safety

  • Inspections: PA DEP performed their annual water supply inspection on July 22-23. The inspector rated the facility as one of the best operated they inspect.
  • Sampling:
    • Bacteriological: 9 samples collected; zero total coliform positives.
    • Chlorine: 5 samples collected (one per week); all met the minimum requirement of 0. 20mg/L free chlorine.
    • PFAS: Third quarter UCMR5 samples collected with no detects.
  • Safety Record: No accidents occurred in July. Personnel have worked 2,008 days (5 years, 7 months) without an accident or injury.
  • Training: Weekly tailgate meetings and crane truck safety presentations were held.

Financial Update

Maintenance Expenditures:

  • Hach: $1,170. 19 (pH probe)
  • The Meter Guy LLC: $725. 00 (Annual meter calibrations)
  • Walmart: $246. 01 (Air hose, sampling disinfectants, sump pump)
  • Heritage Environmental: $129. 50 (Chlorine scale repairs)
  • APPLIED: $152. 29 (Raw water valve solenoid)
  • Long Barn: $60. 97 (Loading dock repairs)
  • Ace Hardware: $19. 99 (Raw water valve repair)

Caps for WTP:

  • Maintenance Cap: Remaining balance is $11,683. 53.
  • Chemical Cap: Remaining balance is $12,906. 83.

Personnel

  • Kyle Smiley: Operator (PA Class A, E, Subclass 1,10,11,12)
  • Tony Perott: Operator (PA Class C, E, Water Subclass 1,6,7,8,12)
  • Cody Williams: Operator in Training (PA Class E, Water Subclass 12)
  • Shawn Jones: Operator in Training (Training for PA DEP exam)
  • Luke Byrne: Project Manager (PA Class A, E, Water Subclass 1,7,8,10,11,12; PA Class A, E, Wastewater)
  • Anthony Perott: Successfully passed all required subclasses and is now a fully licensed operator for the Ebensburg WTP.

Upcoming Items ("On the Radar")

  • DAF Spare parts
  • Upper reservoir inlet valves
  • Online turbidity instrument replacement
  • Lagoon pump installation
← Back to Documents