Inframark WTP Report
View original document →
Ebensburg Municipal Authority: July 2025 WTP Monthly Report
Date: August 25, 2025 Submitted by: Luke Byrne, Inframark
Executive Summary & Operations
- Water Production: The plant treated 36,009,000 gallons of reservoir water in July (avg. 1,161,581 gallons/day).
- Purchased Water: An average of 231,822 gallons per day were purchased from Saltlick and blended into the system. This volume is higher than normal because Nanty Glo is buying water from Ebensburg.
- Nanty Glo Interconnect:
- Nanty Glo shut off their emergency interconnect on July 2nd.
- They reopened it on July 20th requesting 300 GPM due to a filter failure.
- Staff have been operating the WTP at full permit capacity to meet demand. Nanty Glo has exceeded the 15-day purchase limit for an emergency interconnect.
- Reservoir Level: The upper reservoir water level is at -2 ft.
Maintenance & Repairs
Inframark staff completed 56 work orders in July. Key activities included:
- Equipment Issues:
- A Flygt pump in the lagoon wet well suffered a seal failure. The 20-year-old pump was sent to Ram for evaluation; the rebuild cost over 50% of a new unit, so a new pump has been ordered.
- On July 3rd, the raw water valve was not functioning properly due to a faulty 4-20 mA feedback instrument. A new device was installed and is working correctly.
- #2 pump at Saltlick tripped on low voltage but has since operated properly.
- Routine Maintenance:
- Fire extinguisher and ladder inspections.
- Sump pumps exercised.
- DAF Air saturation adjustments and sump level sensor verifications.
- Lagoon motor pull, vault cleaning, and float adjustments.
- Greasing of clarifier drives, finished water pumps/motors, and all pump station motors.
- Cleaning of clarifier troughs, pH/turbidity meters, and the facility.
- Jar testing to optimize chemical usage.
Compliance & Safety
- Inspections: PA DEP performed their annual water supply inspection on July 22-23. The inspector rated the facility as one of the best operated they inspect.
- Sampling:
- Bacteriological: 9 samples collected; zero total coliform positives.
- Chlorine: 5 samples collected (one per week); all met the minimum requirement of 0. 20mg/L free chlorine.
- PFAS: Third quarter UCMR5 samples collected with no detects.
- Safety Record: No accidents occurred in July. Personnel have worked 2,008 days (5 years, 7 months) without an accident or injury.
- Training: Weekly tailgate meetings and crane truck safety presentations were held.
Financial Update
Maintenance Expenditures:
- Hach: $1,170. 19 (pH probe)
- The Meter Guy LLC: $725. 00 (Annual meter calibrations)
- Walmart: $246. 01 (Air hose, sampling disinfectants, sump pump)
- Heritage Environmental: $129. 50 (Chlorine scale repairs)
- APPLIED: $152. 29 (Raw water valve solenoid)
- Long Barn: $60. 97 (Loading dock repairs)
- Ace Hardware: $19. 99 (Raw water valve repair)
Caps for WTP:
- Maintenance Cap: Remaining balance is $11,683. 53.
- Chemical Cap: Remaining balance is $12,906. 83.
Personnel
- Kyle Smiley: Operator (PA Class A, E, Subclass 1,10,11,12)
- Tony Perott: Operator (PA Class C, E, Water Subclass 1,6,7,8,12)
- Cody Williams: Operator in Training (PA Class E, Water Subclass 12)
- Shawn Jones: Operator in Training (Training for PA DEP exam)
- Luke Byrne: Project Manager (PA Class A, E, Water Subclass 1,7,8,10,11,12; PA Class A, E, Wastewater)
- Anthony Perott: Successfully passed all required subclasses and is now a fully licensed operator for the Ebensburg WTP.
Upcoming Items ("On the Radar")
- DAF Spare parts
- Upper reservoir inlet valves
- Online turbidity instrument replacement
- Lagoon pump installation