Documents

Inframark WWTP Report

View original document →

Ebensburg WWTP Monthly Report: January 2026

Date: February 23, 2026 Prepared by: Luke Byrne, Project Manager for Inframark

Executive Summary & Operations

During January 2026, the Ebensburg wastewater treatment plant treated a total of 25,050,400 gallons of wastewater.

  • Sludge Management: The centrifuge was operated weekly, resulting in 13. 0 tons of dry sludge being sent to the landfill.
  • Equipment Maintenance:
    • Centrifuge: Bearing temperatures rose above normal levels due to grease buildup. The issue was resolved by using a portable air compressor to cool the bearings and remove excess grease.
    • SBR#1 Influent Valve: Staff addressed multiple call-outs regarding the valve struggling to open and close during cold weather. The issue was fixed by wrapping heat tape and insulation around the valve and actuator.
  • Power Outages: The facility experienced a recurring monthly power outage. A data recorder has been installed on the transformer to investigate, and Cummins will be onsite in February to inspect the generator transfer switch.
  • Lift Stations: All three lift stations were inspected regularly. No leaks were found, and all floats/transducers are functioning correctly.

Compliance & Plant Operations

All samples collected in January were in compliance with regulations.

  • Testing Schedule:
    • Effluent pH, alkalinity, and dissolved oxygen are analyzed daily.
    • SBR tank testing (Settleability and MLSS) occurs on Mondays, Wednesdays, and Fridays.
    • Influent and effluent compliant testing (TSS, BOD, Phosphorus, Nitrogen, etc. ) is completed on Tuesdays and Thursdays.
  • Routine Tasks: Daily inspections included screening units, grit removal, UV operational checks, and influent/effluent samplers.

Maintenance & Repair

Inframark staff completed 51 work orders in January. Key activities included:

  • Greasing decanters on SBR tanks and the centrifuge.
  • Cleaning the Trojan UV channel, wet well pump floats, and digester weirs/troughs.
  • Adjusting the centrifuge auto greaser and grit blower belt tension.
  • Performing monthly safety inspections and cleaning control building floors.

Financial Update

The following expenditures were recorded for January:

  • Grainger: $166. 87 (Compliance fridge thermometers)

Budget Caps Status:

Category Contract Total per Year Previous Balance Spent This Month Remaining Balance
Maintenance Cap $26,664. 12 $26,664. 12 $166. 87 $26,497. 25
Sludge Cap $85,325. 04 $85,325. 04 $4,005. 08 $81,319. 96
Chemical Cap $23,890. 92 $23,890. 92 $1,997. 34 $21,893. 58

Health & Safety

  • There were no accidents in January.
  • Personnel have worked 2,191 days (6 years and 1 month) without an accident or injury.
  • Ongoing safety protocols include weekly tailgate meetings, safety flash reports, and weekly process control meetings.

Personnel

The following staff members are certified for operations:

  • Randy Lauer (Operator II): PA Class A, E, Wastewater Subclass 1,2,3,4
  • Kyle Smiley (Operator III): PA Class A, E, Water Subclass 1,10,11,12; PA Class A, E, Wastewater Subclass 1
  • Tony Perott (Operator I): PA Class C, E, Water Subclass 1,6,7,8,12
  • Shawn Jones (Mechanic II): NA
  • Joseph Pompa (Operator in Training): Training for PA DEP exam
  • Cody Williams (Operator): PA Class E Water Subclass 12
  • Luke Byrne (Project Manager): PA Class A, E, Water Subclass 1,7,8,10,11,12; PA Class A, E, Wastewater
← Back to Documents