Documents

Inframark WWTP Report

View original document →

Ebensburg WWTP Monthly Report: February 2025

Report Date: March 24, 2025 Submitted by: Luke Byrne, Inframark

Executive Summary & Operations

During February 2025, the Ebensburg wastewater treatment plant treated a total of 29,925,000 gallons of wastewater (averaging 1,068,750 gallons per day). The month was characterized by wet weather with rain, snow, and ice events.

  • Sludge Management: The centrifuge was operated weekly, resulting in 15. 12 tons of dry sludge sent to the landfill. A new contract with Waste Management was negotiated to provide reduced rates for hauling.
  • Equipment Repairs:
    • A new garage door actuator was installed on the centrifuge building.
    • The Trojan UV HMI touchscreen failed (the third time in four years). It was covered under warranty, and the screen was replaced. Additional moisture-reduction measures (outdoor cover, new seal, desiccant beads) were installed.
    • Three bulbs and four wipers were replaced on the UV system.
  • Lift Stations:
    • Emerald Estates: A bad float was discovered causing two pumps to run continuously. The float was replaced, and the pumps are now operating properly.
    • Industrial Park Marine Center: This station continues to experience higher-than-normal flows. Inframark has recommended investigating the area for a possible water main break.

Maintenance & Financials

Inframark staff completed 91 work orders in February. Key maintenance activities included greasing decanters, cleaning screening units and digester weirs, and performing snow removal.

Maintenance Expenditures:

  • LB Water: $1,663. 18 (4-inch valves and pipe)
  • Amazon: $578. 89 (Block heaters for pump stations/batteries)
  • Harbor Freight: $176. 95 (Hoist for hanging headworks heaters)
  • Ace Hardware: $106. 98 (Auto sampler repairs)
  • TEQUIPMENT: $89. 37 (UV HMI cover)
  • Vevor: $48. 81 (Impact sockets)
  • The Long Barn: $39. 90 (Heat tape)

Budget Caps Status:

  • Maintenance Cap: $2,704. 08 spent this month; $22,993. 17 remaining balance.
  • Sludge Cap: $11,413. 60 spent this month; $54,550. 16 remaining balance.
  • Chemical Cap: $3,148. 65 spent this month; $16,955. 28 remaining balance.

Health & Safety

  • There were no accidents in February.
  • Personnel have worked 1,855 days (5 years and 2 months) without an accident or injury.
  • Training topics included weekly tailgate meetings, slips/trips/falls prevention, and Trojan SCADA control SOPs.

Personnel

The following staff members are certified for their respective roles:

  • Randy Lauer (Operator II): PA Class A, E; Wastewater Subclass 1,2,3,4
  • Kyle Smiley (Operator II): PA Class A, E; Water Subclass 1,10,11,12
  • Tony Perott (Operator I): PA Class C, E; Water Subclass 1,6,7,8,12
  • Luke Byrne (Project Manager): PA Class A, E; Water Subclass 1,7,8,10,11,12; Wastewater
  • Shawn Jones & Matt Hull: Operators in Training (Training for PA DEP exam)
← Back to Documents