Documents

Inframark WWTP Report

View original document →

Ebensburg WWTP Monthly Report - February 2024

Report Date: March 25, 2024 Submitted by: Luke Byrne, Project Manager

Executive Summary

During February 2024, the Ebensburg wastewater treatment plant treated a total of 17,318,100 gallons of wastewater. This equates to an average daily flow of 597,176 gallons. All operational and testing requirements were met for the month.

Key maintenance activities included:

  • SBR #2 Mixer: A disconnect was installed after staff discovered a burnt-up switch and damaged wires. The mixer is now running well.
  • Grit Blower: The #2 grit blower was removed from operation and is being rebuilt onsite.
  • Process Water Pumps: Repairs were made to the suction side to prevent cavitation, allowing for continuous operation.
  • New Installations: A laundry sink was installed near the process water pumps for cleaning screener baskets, and a new float ball switch replaced an old failing one.
  • Centrifuge: A new pressure sensor was installed on the sludge feed pump, which is now operating three times more efficiently than the old pump.
  • Electrical: Staff repaired a blown fuse on the DO probe SC100 controller with help from Dodson Electric.
  • Emerald Estates: The automatic transfer switch has been installed, with a full startup scheduled for March 14th.

Operations & Compliance

  • Testing Schedule:
    • SBR tank testing (Settleability, MLSS, MLVSS) occurs Monday, Wednesday, and Friday.
    • Influent and effluent compliant testing (TSS, BOD, Phosphorus, Nitrogen, Ammonia, Fecal Coliform) occurs Tuesdays and Thursdays.
    • Effluent pH and Dissolved Oxygen are tested daily.
  • Reporting: All data is entered into WIMS daily for E-DMR monthly reporting. Monthly reports are sent to the DEP electronically by the 28th of each month.
  • Plant Operations: Routine tasks included inspecting pump stations, screening units, and grit removal processes. Sludge was pumped to digesters for thickening, and the centrifuge was operated daily.

Maintenance & Repair

Inframark staff completed 101 work orders in February. Key tasks included:

  • Greasing decanters on SBR tanks and the screening unit.
  • Replacing a blown fuse on SC100 and installing a new float switch.
  • Installing a pressure sensor on the centrifuge pump line.
  • Replacing four DO probe caps and calibrating them.
  • Installing a grit blower seal kit.
  • Cleaning UV troughs, bulbs, and sensors.
  • Daily hosing of the influent screening unit and weekly greasing of blowers.

Financial Update

Maintenance Expenditures:

  • Hach: $1,098. 76 (DO sensor caps)
  • Ram Industrial: $774. 39 (Flight sensors for process water)
  • Applied: $417. 47 (Bearings for screener)
  • Grainger: $334. 35 (Grit pump repairs)
  • LB Water: $585. 07 (Grit pump repairs)
  • Long Barn: $184. 22 (Wash sink for utility filter cleaning)
  • Harbor Freight: $170. 60 (Grit pump repairs)
  • eBay: $140. 62 (Disconnect for SBR)
  • AutoZone: $37. 09 (Micrometer)
  • Napa: $36. 01 (UV oil filter)
  • Sheetz: $35. 95 (Diesel for pump)
  • Ace Hardware: $72. 66 (Wash sink plumbing)
  • Advance Auto: $66. 76 (Gasket sealer for screw pumps)
  • Battery Guy: $21. 41 (Centrifuge battery)
  • Uni-Mart: $13. 44 (Fuel for pump)

Budget Caps:

  • Maintenance Cap: Contract total is $25,000/year. Previous balance was $23,884. 86. Total spent this month: $3,988. 80. Remaining balance: $19,896. 06.
  • Sludge Cap: Contract total is $80,000/year. Previous balance was $72,878. 31. Total spent this month: $7,146. 21. Remaining balance: $65,732. 10.

Health & Safety

  • There were no accidents in February.
  • Personnel have worked 1,490 days (4 years, 2 months) without an accident or injury.
  • Training and presentations covered weekly tailgate meetings, emergency procedures for chemical spills, and understanding Safety Data Sheets.

Personnel

  • Sharon Burkett: Lead Operator (PA Class A, E, Wastewater Subclass 1,2,3,4,5)
  • Kyle Smiley: Operator II (PA Class A, E, Water Subclass 1)
  • Randy Lauer: Operator II (PA Class A, E, Wastewater Subclass 1,2,3,4)
  • Tony Perott: Operator I (PA Class C, E, Water Subclass 1,6,7,8,12)
  • Shawn Jones: Operator in Training (Training for PA DEP exam)
  • Luke Byrne: Project Manager (PA Class A, E, Water Subclass 1,7,8,10,11; PA Class A, E, Wastewater)
← Back to Documents