Inframark WWTP Report
View original document →
Ebensburg WWTP Monthly Report - February 2024
Report Date: March 25, 2024 Submitted by: Luke Byrne, Project Manager
Executive Summary
During February 2024, the Ebensburg wastewater treatment plant treated a total of 17,318,100 gallons of wastewater. This equates to an average daily flow of 597,176 gallons. All operational and testing requirements were met for the month.
Key maintenance activities included:
- SBR #2 Mixer: A disconnect was installed after staff discovered a burnt-up switch and damaged wires. The mixer is now running well.
- Grit Blower: The #2 grit blower was removed from operation and is being rebuilt onsite.
- Process Water Pumps: Repairs were made to the suction side to prevent cavitation, allowing for continuous operation.
- New Installations: A laundry sink was installed near the process water pumps for cleaning screener baskets, and a new float ball switch replaced an old failing one.
- Centrifuge: A new pressure sensor was installed on the sludge feed pump, which is now operating three times more efficiently than the old pump.
- Electrical: Staff repaired a blown fuse on the DO probe SC100 controller with help from Dodson Electric.
- Emerald Estates: The automatic transfer switch has been installed, with a full startup scheduled for March 14th.
Operations & Compliance
- Testing Schedule:
- SBR tank testing (Settleability, MLSS, MLVSS) occurs Monday, Wednesday, and Friday.
- Influent and effluent compliant testing (TSS, BOD, Phosphorus, Nitrogen, Ammonia, Fecal Coliform) occurs Tuesdays and Thursdays.
- Effluent pH and Dissolved Oxygen are tested daily.
- Reporting: All data is entered into WIMS daily for E-DMR monthly reporting. Monthly reports are sent to the DEP electronically by the 28th of each month.
- Plant Operations: Routine tasks included inspecting pump stations, screening units, and grit removal processes. Sludge was pumped to digesters for thickening, and the centrifuge was operated daily.
Maintenance & Repair
Inframark staff completed 101 work orders in February. Key tasks included:
- Greasing decanters on SBR tanks and the screening unit.
- Replacing a blown fuse on SC100 and installing a new float switch.
- Installing a pressure sensor on the centrifuge pump line.
- Replacing four DO probe caps and calibrating them.
- Installing a grit blower seal kit.
- Cleaning UV troughs, bulbs, and sensors.
- Daily hosing of the influent screening unit and weekly greasing of blowers.
Financial Update
Maintenance Expenditures:
- Hach: $1,098. 76 (DO sensor caps)
- Ram Industrial: $774. 39 (Flight sensors for process water)
- Applied: $417. 47 (Bearings for screener)
- Grainger: $334. 35 (Grit pump repairs)
- LB Water: $585. 07 (Grit pump repairs)
- Long Barn: $184. 22 (Wash sink for utility filter cleaning)
- Harbor Freight: $170. 60 (Grit pump repairs)
- eBay: $140. 62 (Disconnect for SBR)
- AutoZone: $37. 09 (Micrometer)
- Napa: $36. 01 (UV oil filter)
- Sheetz: $35. 95 (Diesel for pump)
- Ace Hardware: $72. 66 (Wash sink plumbing)
- Advance Auto: $66. 76 (Gasket sealer for screw pumps)
- Battery Guy: $21. 41 (Centrifuge battery)
- Uni-Mart: $13. 44 (Fuel for pump)
Budget Caps:
- Maintenance Cap: Contract total is $25,000/year. Previous balance was $23,884. 86. Total spent this month: $3,988. 80. Remaining balance: $19,896. 06.
- Sludge Cap: Contract total is $80,000/year. Previous balance was $72,878. 31. Total spent this month: $7,146. 21. Remaining balance: $65,732. 10.
Health & Safety
- There were no accidents in February.
- Personnel have worked 1,490 days (4 years, 2 months) without an accident or injury.
- Training and presentations covered weekly tailgate meetings, emergency procedures for chemical spills, and understanding Safety Data Sheets.
Personnel
- Sharon Burkett: Lead Operator (PA Class A, E, Wastewater Subclass 1,2,3,4,5)
- Kyle Smiley: Operator II (PA Class A, E, Water Subclass 1)
- Randy Lauer: Operator II (PA Class A, E, Wastewater Subclass 1,2,3,4)
- Tony Perott: Operator I (PA Class C, E, Water Subclass 1,6,7,8,12)
- Shawn Jones: Operator in Training (Training for PA DEP exam)
- Luke Byrne: Project Manager (PA Class A, E, Water Subclass 1,7,8,10,11; PA Class A, E, Wastewater)