Documents

Infrmark Report

View original document →

Ebensburg Municipal Authority Monthly Report (July 2022)

Report Date: August 22, 2022
Prepared by: Inframark Water Infrastructure Operations
Submitted to: Ebensburg Borough Authority Members


Executive Summary

During July 2022, the Ebensburg water treatment plant treated 23,570,000 gallons of reservoir water — averaging 760,323 gallons per day. An additional 57,520 gallons per day were purchased from Saltlick and blended into the distribution system.

  • One power outage occurred but was resolved promptly.
  • Quarterly plant shutdown tests were completed successfully.
  • Lead and Copper sampling bottles were distributed to residents for compliance monitoring under the 2022 schedule.
  • Inframark provided complimentary leak detection services; five leaks were found (one repaired), plus one visual leak discovered by a weekend operator on South Center Street.
  • Meetings held with Stiffler McGraw regarding chemical injection permits and raw water valve rebuild.
  • Borough employees assisted with grass maintenance at the facility — appreciated by Inframark.

On the Radar (Upcoming Projects):

  • Lagoon pond sludge removal
  • Rebuild raw water valve
  • Cleaning and painting elevated tank (will require temporary operational adjustments to maintain pressure)
  • Service clarifiers

Operations & Compliance

Wastewater Treatment Plant (WWTP)

  • Treated 20. 582 million gallons in July.
  • All NPDES permit requirements met — no violations reported.
  • Effluent quality parameters (CBOD5, TSS, pH, DO, Fecal Coliform) all within limits.
  • Daily average flow: 664,000 gallons; monthly total: 20,582,000 gallons.
  • Sludge hauled to landfill: 9. 557 tons.

Water Treatment Plant (WTP)

  • Currently treating 750,000–800,000 gallons/day.
  • Backwash flow rates monitored daily.
  • Filter media inspected daily for irregularities.
  • Online instruments verified multiple times daily.
  • Chemical feed rates adjusted daily to meet demand.
  • Clarifiers monitored for sludge content and settling capability.
  • Lagoons filling — process discussions ongoing.

Compliance Reporting

  • Monthly Operating Report (MOR) compiled from ~20,000 data points sent to PA DEP.
  • August MOR due by September 10, 2022.
  • Disinfection by-product samples collected July 5, 2022 — Haloacetic acids (HAA5) exceeded MCL at Sample Site 701. Tier II public notice issued August 5, 2022.
  • Nine bacteriological samples collected in July — zero total coliform positives.
  • Four chlorine residual samples collected — all met minimum 0. 20 mg/L free chlorine requirement.
  • Instrument calibration and comparative grab sampling performed for accuracy.

Maintenance & Repair

Preventive Maintenance Activities

  • Daily equipment checks and plant rounds.
  • Plant safety inspection completed for the month.
  • Centrifuge run weekly.
  • Grass cut and weeds removed around plant.
  • Control building floors swept/mopped weekly.
  • Mixers pulled from all SBR basins — oil changed and inspected.
  • SBR decanters greased for the month.

Work Orders Completed (67 total in July)

  • Lubricated blower motor
  • Ladder inspections
  • Greased DAF recycle pump and scrapper
  • Fire extinguisher inspection
  • SCBA inspections
  • Sump pumps exercised
  • Eye wash/safety shower inspections
  • Greased clarifier drives
  • Chlorine room alarm test
  • Removed lagoon vault sludge
  • Greased finished water pumps/motors
  • Alternated finished water pumps weekly
  • Cleaned pH and turbidity meters weekly
  • Jar testing to optimize chemical usage
  • Monitored filter beds for deficiencies
  • Cleaned facility

Critical Project

  • Centrifuge main bearings replaced — unit operating very well. Status: Complete. Priority: High. Approved: Yes. Estimated completion: July 11, 2022.

Financial Update

Maintenance Expenditures (July 2022)

Vendor Expense Description
Long Barn $40. 07 Lumber for blocking up centrifuge
EXXONMOBIL $23. 45 Mower fuel, weed eater
Lee’s Hardware $19. 24 Fittings to repair water line
Ace Hardware $232. 80 PVC fittings, drain opener, etc.
Lubrication Eng. $425. 76 Hydraulic fluid for centrifuge
EXXONMOBIL $21. 27 Mower fuel, weed eater
Sheetz $23. 20 Mower fuel, weed eater
EXXONMOBIL $24. 83 Mower fuel, weed eater
Walmart $62. 37 Battery backup supply, markers
Sheetz $24. 80 Mower fuel, weed eater
Ebensburg NAPA $466. 33 Belts for blowers
E-Rigging $106. 68 Lifting straps for centrifuge
Lubrication Eng. $212. 83 Blower oil
Total $1,683. 63

Caps (Wastewater)

Cap Type Monthly Cap July 2022 Spent Contract YTD Remaining Balance
Maintenance Cap $1,914. 47 $1,683. 63 $9,023. 84 $14,871. 40
Sludge Cap $6,317. 77 $4,088. 38 $24,188. 35 $54,666. 05

Caps (Water Treatment Plant)

Cap Type Contract Total/Year Previous Balance Spent This Month Remaining Balance
Maintenance Cap $26,010. 00 $19,701. 55 $91. 99 $19,609. 56

Additional Maintenance Expenditures (WTP)

Vendor Expense Description
Kaza Fire Equip. $58. 72 Annual fire extinguisher insp.
Tractor Supply $33. 27 Bearing grease

Health & Safety

  • Wastewater Plant: Employees worked 6,390 days without a lost-time injury or recordable incident as of end of July. Daily tailgate meetings held.
  • Water Treatment Plant: No accidents in July. Personnel have worked 912 days (2 years 6 months) without an accident/injury.
  • Training topics covered: Weekly tailgate meetings, COVID-19 updates, PPE, workplace safety awareness.

Personnel

Wastewater Treatment Plant Staff

Name Title Certifications
Jerry Shupe Jr. Vice President, Mid-Atlantic Region
Mike Montgomery Plant Manager PA Class A, E Subclass 1,2,3,4
Sharon Burkett Lab Manager PA Class A, E Subclass 1,2,3,4,5
Randy Lauer Operator PA Class A, E Subclass 1,2,3,4
Ryan Lanzendorfer Operator in Training None
Kyle Smiley Operator in Training None

Water Treatment Plant Staff

Name Title Certifications
Luke Byrne Water Plant Manager PA Class A, E, Water Subclass 1,7,8,10,11
Kyle Smiley Operator PA Class A, E, Subclass 1
Ryan Lanzendorfer Operator in Training

Appendix

  • July’s 2022 Discharge Monitoring Report is available upon request.
  • Signed by: Michael J. Montgomery, Plant Manager (WWTP)

Report submitted via letter dated August 22, 2022, addressed to Ebensburg Borough, 300 West High Street, Ebensburg, PA 15931. Letter signed by Luke Byrne.

← Back to Documents