Documents

nframark Reports

View original document →

Ebensburg Water Treatment Facility Report (October 2022)

Submitted by: Inframark Date of Letter: November 22, 2022 Submitted to: Ebensburg Borough Authority Members

Executive Summary

  • Production Volume: The plant treated 29,433,000 gallons of reservoir water in October. This averages to 949,452 gallons per day.
  • Water Purchases: An average of 124,066 gallons per day was purchased from Saltlick and blended into the system. This increase is attributed to Nanty Glo purchasing water at the end of the month.
  • Water Quality & Compliance:
    • On October 4th, fourth-quarter disinfection by-product samples were collected. Results exceeded the Maximum Contaminant Level (MCL). A public notice was issued on November 9th.
    • Follow-up samples taken on October 27th showed significantly lower by-product levels when additional water was moved through the Ogden tank site.
    • On October 25th, PA DEP representatives collected raw water samples for cyanotoxins. A low detection was found, but it did not exceed the Health Advisory Level for finished water (0. 3 micrograms/Liter).
  • Infrastructure Updates:
    • A new water line was installed into the treatment facility, a recommendation made in 2020. Inframark is currently working on interior plumbing connections.
    • The elevated tank at Hillcrest has been drained for repairs, with work nearing completion. Inframark is coordinating with the public works director to return it to normal operation.

Operations & Maintenance

  • Compliance:
    • Monthly Operating Reports (MOR) containing over 20,000 data points were submitted to the PA DEP.
    • Nine bacteriological samples were collected; zero were total coliform positive.
    • Four chlorine level samples were taken, all meeting the minimum requirement of 0. 20mg/L.
  • Plant Operations:
    • Daily production fluctuated between 700,000 and 1,350,000 gallons.
    • Nanty Glo purchased between 360,000 and 576,000 gallons per day.
    • Routine maintenance included daily filter washing, clarifier monitoring, and DAF (Dissolved Air Flotation) adjustments.
  • Maintenance & Repair: Staff completed 87 work orders in October, including:
    • Lubricating blowers and pumps.
    • Inspecting ladders, fire extinguishers, and SCBA equipment.
    • Cleaning pH and turbidity meters weekly.
    • Replacing fluorescent light bulbs and an ASCO solenoid on a raw water valve.

Financial Update (Water)

  • Maintenance Expenditures:
    • Scanlan Electric: $117. 47 (4-foot fluorescent lights/photo eye)
    • Ace Hardware: $424. 16 (Pressure reducer/back flow preventer/fittings)
  • Maintenance Cap Status:
    • Contract Total per Year: $26,010. 00
    • Previous Balance: $13,171. 63
    • Total Spent This Month: $541. 63
    • Remaining Balance: $13,713. 26

Personnel & Safety

  • Safety Record: No accidents occurred in October. Personnel have worked 1,004 days (2 years, 9 months) without an injury.
  • Training: Weekly tailgate meetings, COVID-19 updates, and Personal Protective Equipment (PPE) reviews were conducted.
  • Staff Certifications:
    • Luke Byrne (Water Plant Manager): PA Class A, E, Water Subclass 1,7,8,10,11
    • Kyle Smiley (Operator): PA Class A, E, Subclass 1

Ebensburg Wastewater Treatment Plant Report (October 2022)

Submitted by: Inframark Date of Letter: November 21, 2022 Submitted to: Ebensburg Borough Authority Members

Executive Summary

  • Production Volume: The plant treated 21. 179 million gallons of clean water to Howells Run, averaging . 683 million gallons per day.
  • Sludge Management: The centrifuge was run two times a week, resulting in 9. 075 tons of sludge sent to the landfill.
  • Upcoming Projects: The Borough Engineer is investigating the installation of a new 20" influent valve for SBR tank #2.

Operations & Maintenance

  • Compliance:
    • SBR tank testing for process control was performed on Mondays, Wednesdays, and Fridays.
    • Influent and effluent compliant testing for DEP reporting was done on Tuesdays and Thursdays.
    • All data is entered daily, and monthly reports are sent electronically to the DEP by the 28th of each month.
  • Plant Operations:
    • Daily plant rounds and equipment checks were performed multiple times per shift.
    • The influent screening unit was hosed and cleaned daily.
  • Maintenance & Repair:
    • Cleaned U. V. banks and refilled with lime.
    • Greased decanters on SBR tanks.
    • Completed monthly safety inspections.
    • Cleaned centrifuge and control building floors.

Financial Update (Wastewater)

  • Maintenance Expenditures:
    • EXXONMOBIL: $36. 00 (Mower gas)
    • Ace Hardware: $152. 12 (Batteries, snow shovel, drain opener, flashlight, caulking, adjustable wrench)
    • Kone Cranes: $650. 00 (Crane inspection)
    • Home Depot: $36. 96 (4 - 5-gallon buckets)
  • Caps for WWTP Status:
    • Maintenance Cap:
      • Contract Total per Year: $23,895. 24
      • October 2022 Spend: $1,311. 26
      • Contract Year to Date: $21,825. 98
      • Remaining Balance: $2,069. 26
    • Sludge:
      • Contract Total per Year: $78,854. 40
      • October 2022 Spend: $13,508. 89
      • Contract Year to Date: $48,918. 02
      • Remaining Balance: $29,936. 38

Personnel & Safety

  • Safety Record: No accidents occurred in October. Personnel have worked 6,480 days (17 years, 7 months) without an injury.
  • Training: Weekly tailgate meetings, COVID-19 updates, PPE reviews, and cyber security updates were conducted.
  • Staff Certifications:
    • Michael Montgomery (Plant Manager): PA Class A, E, Wastewater Subclass 1,2,3,4
    • Sharon Burkett (Lab Supervisor): PA Class A, E, Wastewater Subclass 1,2,3,4,5
    • Kyle Smiley (Operator): PA Class A, E, Water Subclass 1
    • Ryan Lanzendorfer (Operator in Training): Certification details not listed.
← Back to Documents