nframark Reports
View original document →
Ebensburg Water Treatment Facility Report (October 2022)
Submitted by: Inframark Date of Letter: November 22, 2022 Submitted to: Ebensburg Borough Authority Members
Executive Summary
- Production Volume: The plant treated 29,433,000 gallons of reservoir water in October. This averages to 949,452 gallons per day.
- Water Purchases: An average of 124,066 gallons per day was purchased from Saltlick and blended into the system. This increase is attributed to Nanty Glo purchasing water at the end of the month.
- Water Quality & Compliance:
- On October 4th, fourth-quarter disinfection by-product samples were collected. Results exceeded the Maximum Contaminant Level (MCL). A public notice was issued on November 9th.
- Follow-up samples taken on October 27th showed significantly lower by-product levels when additional water was moved through the Ogden tank site.
- On October 25th, PA DEP representatives collected raw water samples for cyanotoxins. A low detection was found, but it did not exceed the Health Advisory Level for finished water (0. 3 micrograms/Liter).
- Infrastructure Updates:
- A new water line was installed into the treatment facility, a recommendation made in 2020. Inframark is currently working on interior plumbing connections.
- The elevated tank at Hillcrest has been drained for repairs, with work nearing completion. Inframark is coordinating with the public works director to return it to normal operation.
Operations & Maintenance
- Compliance:
- Monthly Operating Reports (MOR) containing over 20,000 data points were submitted to the PA DEP.
- Nine bacteriological samples were collected; zero were total coliform positive.
- Four chlorine level samples were taken, all meeting the minimum requirement of 0. 20mg/L.
- Plant Operations:
- Daily production fluctuated between 700,000 and 1,350,000 gallons.
- Nanty Glo purchased between 360,000 and 576,000 gallons per day.
- Routine maintenance included daily filter washing, clarifier monitoring, and DAF (Dissolved Air Flotation) adjustments.
- Maintenance & Repair: Staff completed 87 work orders in October, including:
- Lubricating blowers and pumps.
- Inspecting ladders, fire extinguishers, and SCBA equipment.
- Cleaning pH and turbidity meters weekly.
- Replacing fluorescent light bulbs and an ASCO solenoid on a raw water valve.
Financial Update (Water)
- Maintenance Expenditures:
- Scanlan Electric: $117. 47 (4-foot fluorescent lights/photo eye)
- Ace Hardware: $424. 16 (Pressure reducer/back flow preventer/fittings)
- Maintenance Cap Status:
- Contract Total per Year: $26,010. 00
- Previous Balance: $13,171. 63
- Total Spent This Month: $541. 63
- Remaining Balance: $13,713. 26
Personnel & Safety
- Safety Record: No accidents occurred in October. Personnel have worked 1,004 days (2 years, 9 months) without an injury.
- Training: Weekly tailgate meetings, COVID-19 updates, and Personal Protective Equipment (PPE) reviews were conducted.
- Staff Certifications:
- Luke Byrne (Water Plant Manager): PA Class A, E, Water Subclass 1,7,8,10,11
- Kyle Smiley (Operator): PA Class A, E, Subclass 1
Ebensburg Wastewater Treatment Plant Report (October 2022)
Submitted by: Inframark Date of Letter: November 21, 2022 Submitted to: Ebensburg Borough Authority Members
Executive Summary
- Production Volume: The plant treated 21. 179 million gallons of clean water to Howells Run, averaging . 683 million gallons per day.
- Sludge Management: The centrifuge was run two times a week, resulting in 9. 075 tons of sludge sent to the landfill.
- Upcoming Projects: The Borough Engineer is investigating the installation of a new 20" influent valve for SBR tank #2.
Operations & Maintenance
- Compliance:
- SBR tank testing for process control was performed on Mondays, Wednesdays, and Fridays.
- Influent and effluent compliant testing for DEP reporting was done on Tuesdays and Thursdays.
- All data is entered daily, and monthly reports are sent electronically to the DEP by the 28th of each month.
- Plant Operations:
- Daily plant rounds and equipment checks were performed multiple times per shift.
- The influent screening unit was hosed and cleaned daily.
- Maintenance & Repair:
- Cleaned U. V. banks and refilled with lime.
- Greased decanters on SBR tanks.
- Completed monthly safety inspections.
- Cleaned centrifuge and control building floors.
Financial Update (Wastewater)
- Maintenance Expenditures:
- EXXONMOBIL: $36. 00 (Mower gas)
- Ace Hardware: $152. 12 (Batteries, snow shovel, drain opener, flashlight, caulking, adjustable wrench)
- Kone Cranes: $650. 00 (Crane inspection)
- Home Depot: $36. 96 (4 - 5-gallon buckets)
- Caps for WWTP Status:
- Maintenance Cap:
- Contract Total per Year: $23,895. 24
- October 2022 Spend: $1,311. 26
- Contract Year to Date: $21,825. 98
- Remaining Balance: $2,069. 26
- Sludge:
- Contract Total per Year: $78,854. 40
- October 2022 Spend: $13,508. 89
- Contract Year to Date: $48,918. 02
- Remaining Balance: $29,936. 38
- Maintenance Cap:
Personnel & Safety
- Safety Record: No accidents occurred in October. Personnel have worked 6,480 days (17 years, 7 months) without an injury.
- Training: Weekly tailgate meetings, COVID-19 updates, PPE reviews, and cyber security updates were conducted.
- Staff Certifications:
- Michael Montgomery (Plant Manager): PA Class A, E, Wastewater Subclass 1,2,3,4
- Sharon Burkett (Lab Supervisor): PA Class A, E, Wastewater Subclass 1,2,3,4,5
- Kyle Smiley (Operator): PA Class A, E, Water Subclass 1
- Ryan Lanzendorfer (Operator in Training): Certification details not listed.